22 October 2026 · JY and Aiting. Every past figure is from our own monthly accounts (Feb 2024 to Sep 2026), excluding GST. The projection uses the same cost base. What we have not been able to confirm is listed at the end.
From 780 Upper Serangoon Road #01-02 (USR Junction, 2,296 sq ft) to 154 Hougang Street 11 #01-196 (a ground-floor HDB shop, 3,304 sq ft). The new centre is a 5-minute walk (355 m) away, in the same Kovan catchment and on the same bus corridor.
Distances in the pop-ups are straight-line from the new centre. Map © OpenStreetMap contributors.
| 780 USR (now) | Blk 154 Hougang St 11 | |
|---|---|---|
| Size | 2,296 sq ft | 3,304 sq ft |
| Rent | $18.8k now ($8.20 psf); $19.9k-20.7k on the renewal from Feb 2027 ($8.70-9.00 psf) | $2,500 ($0.76 psf), plus S&CC of about $700 |
| Children it can hold | 96 | about 130 |
| Break-even | about 52 children | about 28 children |
| Landlord | Private owner; the renewal lets them end the lease on 3 months' notice if the building is sold | HDB; 3-year tenancy plus a 3-year option |
| Getting there | Main road bus stops at the door | Bus 113 at the door; the main stops are a 6-7 minute walk (8-10 for a child) |
We opened in February 2024. Each January a new intake of Primary 1 children joins, then numbers drift down over the year. Each year the starting point has been higher: 18 at the 2024 peak, 39 in January 2025 and 53 in January 2026.
Monthly figures are lumpy: enrichment trainers are paid termly and materials fees are billed twice a year. The annual totals are the reliable view.
| S$, ex GST | Before opening Nov 2023-Jan 2024 | 2024 Feb-Dec, 11 mths | 2025 12 mths | 2026 Jan-Sep, 9 mths | Now, per month Jul-Sep 2026 |
|---|---|---|---|---|---|
| Average children in student care | |||||
| Children (average) | - | 12 | 33 | 45 | 42 |
| Revenue | |||||
| School fees (student care) | - | 94,816 | 272,589 | 272,609 | 29,061 |
| Flexi care | - | 5,450 | 17,500 | 9,816 | 1,605 |
| Enrichment classes | - | 9,634 | 52,907 | 48,100 | 5,737 |
| Holiday programme | - | 14,831 | 15,886 | 13,863 | 734 |
| Transport charged to parents | - | 6,000 | 16,650 | 30,450 | 3,600 |
| Materials, uniform, insurance | - | 5,548 | 15,660 | 18,270 | 2,330 |
| Registration fees | - | 1,940 | 3,840 | 3,150 | 53 |
| Other | - | - | 548 | 92 | 31 |
| Total revenue | - | 138,219 | 395,580 | 396,350 | 43,152 |
| Operating costs | |||||
| Rent (780 USR) | - | 187,760 | 225,312 | 168,984 | 18,776 |
| Utilities and aircon | - | 2,495 | 10,872 | 15,833 | 639 |
| Staff salaries | - | 66,277 | 140,051 | 106,748 | 11,792 |
| CPF and SDL | - | 20,888 | 16,322 | 44,757 | 5,060 |
| Royalties and fees to HQ | - | 11,845 | 34,116 | 33,354 | 3,597 |
| Enrichment trainers | - | 9,239 | 16,313 | 11,362 | 1,898 |
| Food | - | 11,075 | 22,787 | 21,600 | 2,339 |
| School bus | - | 5,400 | 20,735 | 19,780 | 1,600 |
| Materials and consumables | - | 5,787 | 6,694 | 3,977 | 777 |
| Excursions and holiday costs | - | 3,219 | 5,763 | 4,128 | 528 |
| Marketing | - | 7,749 | 4,800 | 4,865 | 67 |
| Insurance | - | 397 | - | 790 | - |
| Accounting and professional | - | - | 2,520 | 2,520 | - |
| Repairs and maintenance | - | 2,630 | 733 | 605 | - |
| IT, phone and admin | - | 9,682 | 6,082 | 4,266 | 480 |
| Other | - | 731 | 1,547 | 228 | 76 |
| Total operating costs | - | 345,174 | 514,648 | 443,797 | 47,628 |
| Operating profit (EBITDA) | - | (206,956) | (119,068) | (47,447) | (4,476) |
| Below the line | |||||
| Depreciation of the fit-out | - | (32,293) | (35,229) | (26,422) | (2,936) |
| Set-up costs expensed | (139,809) | (11,653) | (11,240) | - | - |
| Net loss before tax | (139,809) | (250,902) | (165,537) | (73,869) | (7,412) |
Revenue is booked in the month the service was delivered. Deposits are excluded because they are refundable. Costs exclude GST, and exclude $86k of staff costs that belong to our sister business, Little Forest (details in section 7). Depreciation follows our accountant: the fit-out over 5 years and equipment over 3 years, $35k a year in total. "Set-up costs expensed" means items the accountant charged straight to the P&L rather than depreciating: in 2023 the $120k franchise fee and the $18.8k goodwill paid to the landlord, later the enrichment starter kits.
The HDB tenancy runs from January 2027 for 3 years, with an option for 3 more, so the projection runs from 2027 to 2032. The children move in on 1 April 2027 after a 3-month fit-out. Until then we stay at 780 on a short extension. The cost base is today's actual costs, and prices rise 3% a year.
| S$, ex GST | 2027 Term 1 | 2028 Term 1 | 2029 Term 1 | 2030 Term 2 | 2031 Term 2 | 2032 Term 2 |
|---|---|---|---|---|---|---|
| Children (average) | 60 | 74 | 87 | 96 | 103 | 108 |
| Staff (headcount) | 7 | 9 | 10 | 11 | 12 | 13 |
| Revenue | ||||||
| School fees | 594,751 | 758,378 | 909,533 | 1,037,332 | 1,147,135 | 1,243,141 |
| Enrichment, holiday, transport, other | 103,404 | 106,506 | 109,701 | 112,992 | 116,382 | 119,874 |
| Total revenue | 698,155 | 864,884 | 1,019,234 | 1,150,325 | 1,263,517 | 1,363,015 |
| Operating costs | ||||||
| Staff incl. CPF | (256,500) | (328,776) | (398,156) | (453,372) | (504,115) | (546,018) |
| Royalties to HQ (9.3%) | (64,928) | (80,434) | (94,789) | (106,980) | (117,507) | (126,760) |
| Food | (43,255) | (53,548) | (62,351) | (69,040) | (74,125) | (77,989) |
| Other running costs | (77,160) | (79,475) | (81,859) | (84,315) | (86,844) | (89,450) |
| Rent, 780 USR (until move) | (58,675) | - | - | - | - | - |
| Rent, Hougang | (25,000) | (30,000) | (30,000) | (33,000) | (33,000) | (33,000) |
| S&CC, aircon servicing, extra power | (16,250) | (16,250) | (16,250) | (16,250) | (16,250) | (16,250) |
| Operating profit (EBITDA) | 156,387 | 276,401 | 335,830 | 387,367 | 431,676 | 473,548 |
| Below the line | ||||||
| Reinstate 780 USR | (45,000) | - | - | - | - | - |
| HQ relocation fee, stamp duty | (15,360) | - | - | - | - | - |
| Franchise renewal (Nov 2028) | - | (104,000) | - | - | - | - |
| Depreciation, Hougang fit-out | (57,000) | (57,000) | (57,000) | (57,000) | (57,000) | - |
| Depreciation and write-off, 780 fit-out | (56,361) | - | - | - | - | - |
| Net profit before tax | (17,334) | 115,401 | 278,830 | 330,367 | 374,676 | 473,548 |
| Cash | ||||||
| Fit-out (capex) | (285,000) | - | - | - | - | - |
| Deposits (paid) / returned | 53,828 | - | - | - | - | - |
| Cash generated | (135,145) | 172,401 | 335,830 | 387,367 | 431,676 | 473,548 |
| Net profit before tax | 2027 | 2028 | 2029 | 2030 | 2031 | 2032 | 6 years |
|---|---|---|---|---|---|---|---|
| Move, upside | 12,577 | 144,586 | 301,765 | 349,185 | 398,528 | 481,808 | 1,688,449 |
| Move, central case | (17,334) | 115,401 | 278,830 | 330,367 | 374,676 | 473,548 | 1,555,488 |
| Move, downside | (50,151) | (12,970) | 79,035 | 65,492 | 60,459 | 127,126 | 268,991 |
| Stay at 780 USR | 357 | (33,742) | 133,439 | 123,993 | 135,599 | 149,680 | 509,325 |
| Stay, and a competitor opens nearby (compare with the downside) | (1,625) | (125,935) | (21,938) | (60,619) | (74,563) | (82,804) | (367,484) |
| Average children | |||||||
| Move, upside | 65 | 79 | 90 | 99 | 105 | 110 | |
| Move, central case | 60 | 74 | 87 | 96 | 103 | 108 | |
| Move, downside | 54 | 47 | 44 | 42 | 41 | 40 | |
| Stay at 780 USR (capacity 96) | 65 | 79 | 85 | 85 | 85 | 85 | |
| Stay, competitor nearby | 63 | 55 | 49 | 46 | 43 | 42 | |
In the downside case the centre averages only 40-50 children, about where we are today. At 780 that headcount loses money. At Hougang it still makes $60k-79k a year before tax from 2029. If we stayed at 780 in the same situation, we would lose about -$367k over the 6 years (last row of the table). The rent saving does the work, not the growth assumptions.
| Where the $342k goes (to Apr 2027, central case) | S$ |
|---|---|
| Fit-out of the bare HDB shop (range $230k-340k) | 285,000 |
| Reinstating 780 USR on exit | 45,000 |
| HQ relocation fee, stamp duty, HDB deposit | 17,860 |
| Operating losses Oct-Dec 2026 (still at 780) | 27,395 |
| Less: operating profit Jan-Apr 2027 (the January intake joins) | (33,381) |
| Lowest point, April 2027 | 341,874 |
| Less: 780 USR deposit returned, May 2027 | (56,328) |
| Less: GST on the fit-out, reclaimed in the next GST return | (about 26,000) |
| Longer-term funding needed (the rest is a 1-3 month bridge) | about 260,000-300,000 |
From 2028 the centre should generate about $170k-340k of cash a year in the central case, after the franchise renewal. So a $300k loan could be repaid within about 2 years in the central case and about 3 in the downside. Interest is not in these figures: at about 7%, $300k costs about $21k a year while it is outstanding.
We cannot fund this ourselves alone right now, and we want to do it in a way the business can carry if things go slower than planned. These are the routes we have looked at:
| Route | What we think |
|---|---|
| Bank SME loan (Enterprise Financing Scheme, government risk-share) | The cheapest money, but our history is losses, so banks may want personal guarantees or collateral, or decline. The projection is our main argument. |
| Spread the fit-out cost | Ask the contractor for staged payments over 12-24 months, or lease the aircon and equipment. This could cut the upfront need by $50k-100k. |
| HQ support | Ask PlayFACTO HQ for the relocation to restart our franchise term, which avoids the $104k renewal in 2028, plus a waived relocation fee and a royalty holiday. Not agreed yet. |
| Private loan at a fixed return | From people who know us, repaid over 2-3 years from the cash flow above. We prefer this to selling shares. |
| An equity partner in the outlet | Possible, but giving up a share of a centre that should make about $300k a year from 2029 is expensive money. |
| Little Forest repays PlayFACTO | Our sister business owes PlayFACTO about $86k for shared staff. Settling it would cover about a third of the need. A bank reading our filed accounts will also see these costs inside PlayFACTO's losses, so we would explain them. |
| Phase the fit-out | Build what we need to open (classrooms, toilets, pantry, aircon) and finish the rest from cash flow. This brings the cost closer to the $230k low case. |
This is what we paid to fit out 780 USR in January-February 2024, taken line by line from the signed bill of quantities and the subcontractor invoices. The main contractor was VM Education, PlayFACTO HQ's own company (it also bills our franchise fees). Its BOQ "PFS_KOVAN v2.0" (26 Jan 2024) came to $127,758 and matches the final invoice to the cent. Sprinklers, aircon ducting, CCTV and door access were separate contractors. All figures are S$ excluding GST, at 2024 prices.
| Item | Qty | Unit | Rate | Amount | Per unit / m2 | Hougang |
|---|---|---|---|---|---|---|
| VM Education: preliminaries | 2,250 | |||||
| 1.1 Site marking and general protection | 1 | sum | 400 | Redo | ||
| 1.2 General cleaning after renovation | 1 | sum | 600 | Redo | ||
| 1.3 Daily rubbish clearance | 1 | sum | 500 | Redo | ||
| 1.4 Project insurance | 1 | sum | 750 | Redo | ||
| VM Education: professional fees | 7,600 | |||||
| 2.1 QP submission fees (architectural) | 1 | sum | 3,800 | Redo | ||
| 2.2 M&E submission incl. processing fees / RI | 1 | sum | 3,600 | Redo | ||
| 2.4 LEW single-line drawing | 1 | sum | 200 | Redo | ||
| VM Education: walls | 21,155 | |||||
| 4.1 75mm gypsum partition, 12.5mm board both sides, metal studs @600, 40kg rockwool, to 3.0m | 201 | sqm | $55 | 11,055 | Redo | |
| 4.2 Extra for curved partition at Makers' Space | 1 | sum | 1,000 | Redo | ||
| 4.3 Timber trellis feature wall in laminate, incl. curve and light cove (est. 29 m2) | 1 | sum | 7,250 | $250/m2 | Redo | |
| 4.4 Plywood reinforcement in partition for TVs | 6 | no | $100 | 600 | Redo | |
| 4.5 Plywood backing for green wall, 3.85m x 3.0m | 1 | no | 1,250 | $108/m2 | Redo | |
| VM Education: ceiling | 9,560 | |||||
| 5.1 Plaster ceiling, 3.0m high | 224 | sqm | $40 | 8,960 | Redo | |
| 5.2 Access panel 450 x 450mm | 6 | no | $100 | 600 | Redo | |
| VM Education: doors | 15,200 | |||||
| 6.1 Main glass door: remove handles, seal holes | 1 | no | 200 | Redo | ||
| 6.2b Cut existing timber door bottoms for vinyl | 2 | no | $350 | 700 | Redo | |
| 6.3 D01 swing timber door, laminate, with ironmongery, 1.0 x 2.1m (no closer) | 5 | no | $900 | 4,500 | Redo | |
| 6.4a D02 folding timber doors, laminate, 3.7 x 2.4m | 1 | no | 6,100 | $687/m2 | Redo | |
| 6.4b Metal reinforcement above folding door, 3.7m | 1 | no | 1,500 | $405/m | Redo | |
| 6.5a D03 12mm tempered frameless glass swing door, 1.0 x 2.1m | 1 | no | 1,000 | $476/m2 | Redo | |
| 6.5b 12mm tempered fixed glass panel, exposed aluminium frame, 2.025 x 2.1m | 1 | sum | 1,200 | $282/m2 | Redo | |
| VM Education: painting | 6,500 | |||||
| 7.1 White matt emulsion, new partitions and existing internal walls | 621 | sqm | 4,500 | $7.25/sqm | Redo | |
| 7.2 White matt emulsion, plaster ceiling | 224 | sqm | 2,000 | $8.93/sqm | Redo | |
| VM Education: carpentry | 28,760 | |||||
| 8.1 JN01 reception low open shoe cabinet, laminate, 1.5m + 1.8m x 1.51m H x 0.35m D | 1 | no | 3,925 | $1,189/m run | Maybe | |
| 8.2 JN02 two-tier serving counter, laminate, solid-surface ledge, 1.4m x 1.1m H | 1 | no | 2,675 | $1,911/m run | Maybe | |
| 8.3a JN03 pantry base cabinet, 1.65 + 2.4m x 0.86m H, solid-surface top, window box-up | 1 | no | 4,900 | $1,210/m run | Redo | |
| 8.3b JN03 pantry wall-hung cabinet 3.95m x 1.44m H, incl. bulkhead | 1 | no | 2,650 | $671/m run | Redo | |
| 8.3c Glass backsplash + ply backing, 2.4 x 0.7m | 1 | no | 900 | $536/m2 | Redo | |
| 8.4 JN04 feature open bookshelf, laminate, 2.1 x 2.1m x 0.35m D | 1 | no | 4,200 | $952/m2 | Maybe | |
| 8.5a JN05 full-height storage cabinet 0.9m x 3.0m H, incl. bulkhead | 1 | no | 1,100 | $1,222/m run | Redo | |
| 8.5c JN06 wash-basin counter, solid surface, metal support, mirror, base cabinet, 1.2m | 1 | no | 4,650 | $3,875/m run | Redo | |
| 8.6 JN07 laminate wall panel for signage, 1.5 x 3.0m | 1 | no | 1,200 | $267/m2 | Redo | |
| 8.8 Whiteboard 1.8 x 1.2m | 7 | no | $280 | 1,960 | Move | |
| 8.9 Notice board, laminate, 2.4 x 1.2m | 1 | no | $600 | 600 | Move | |
| VM Education: loose furniture | 6,360 | |||||
| 9.1 Rectangular table, lower primary height, 1.2 x 0.6m | 8 | no | $165 | 1,320 | Move | |
| 9.2 Primary school table, 1.2 x 0.6m | 16 | no | $165 | 2,640 | Move | |
| 9.3 Classroom chair, full PP, 340mm seat | 32 | no | $25 | 800 | Move | |
| 9.4 Classroom chair, full PP, 390mm seat | 64 | no | $25 | 1,600 | Move | |
| VM Education: electrical | 15,562 | |||||
| 10.1 Temporary power and lighting for works | 1 | no | $350 | 350 | Redo | |
| 10.2 Earthing / bonding to sprinkler pipe, water pipe, trunking | 1 | no | $200 | 200 | Redo | |
| 10.4 Lighting point | 70 | no | $55 | 3,850 | Redo | |
| 10.5 Emergency-light point | 20 | no | $55 | 1,100 | Redo | |
| 10.6 Single 13A socket | 8 | no | $70 | 560 | Redo | |
| 10.7 Twin 13A socket | 16 | no | $90 | 1,440 | Redo | |
| 10.8 Data point | 3 | no | $120 | 360 | Redo | |
| 10.9 20A DP isolator for aircon | 4 | no | $180 | 720 | Redo | |
| 10.10 Emergency light fitting (UFO type) | 15 | no | $90 | 1,350 | Redo | |
| 10.11 Exit light with battery pack | 5 | no | $110 | 550 | Redo | |
| 10.12 Emergency strobe light and wiring | 1 | no | $150 | 150 | Redo | |
| 10.13 163A 3-phase distribution board | 1 | no | $850 | 850 | Redo | |
| 10.14 Sub-main cables, building isolator to unit DB | 8 | no | $55 | 400 | priced at $400, not 8 x $55 | Redo |
| 10.15 Install light fixtures (labour) | 68 | no | $20 | 1,360 | Redo | |
| 10.16 Install CCTV cameras (labour) | 5 | no | $30 | 150 | Redo | |
| 10.17a LED round panel light 12W | 46 | no | $22 | 1,012 | Maybe | |
| 10.17b Corridor light (IKEA) | 8 | no | $45 | 360 | Maybe | |
| 10.17c Light track 1.5m | 4 | no | $20 | 80 | Maybe | |
| 10.17d Track light fitting with bulb | 12 | no | $15 | 180 | Maybe | |
| 10.17e Twin spot light at entrance | 2 | no | $45 | 90 | Maybe | |
| 10.17f LED strip light and driver in light cove | 1 | sum | 450 | Redo | ||
| VM Education: plumbing | 4,960 | |||||
| 11.1 Exposed supply/discharge pipes to pantry sink, 2 basins, 2 showers; install sink and taps | 1 | sum | 2,500 | Redo | ||
| 11.2 Plumbing fittings (sink, taps, bottle trap) | 1 | sum | 960 | Redo | ||
| 11.3 Plumbing drawing and QP plumber endorsement | 1 | sum | 1,500 | Redo | ||
| VM Education: flooring | 8,750 | |||||
| 12.1 5mm click vinyl flooring | 268.8 | sqm | 8,500 | $31.62/sqm | Redo | |
| 12.2 Artificial lawn carpet | 15.6 | sqm | 250 | $16.03/sqm | Maybe | |
| VM Education: others | 1,101 | |||||
| 13.1 10mm acrylic cut-out logo, 891 x 723mm | 1 | no | 900 | Move | ||
| 13.2 Branding stickers | 1 | sum | 1 | Redo | ||
| 13.6 3kg dry-powder fire extinguisher | 2 | no | $100 | 200 | Move | |
| Design (VM Education) | 8,000 | |||||
| VM231221 Renovation management and design fee | 1 | sum | 8,000 | $3.48/sq ft | Redo | |
| Sprinklers (Chao Seng) | 9,540 | |||||
| 24-6155 Royal flush sprinkler heads incl. range piping | 33 | no | $180 | 5,940 | Redo | |
| 24-6155 Branch main pipe | 1 | sum | 2,500 | Redo | ||
| 24-6155 Tee-off from existing main | 1 | sum | 700 | Redo | ||
| 24-6155 Drain-down fees | 1 | sum | 400 | Redo | ||
| Aircon ducting (DF Engineering) | 15,730 | |||||
| 2402001 Supply air ducting (to landlord's existing units) | 6 | lot | $1,125 | 6,750 | Redo | |
| 2402001 4-way supply diffuser | 24 | no | $250 | 6,000 | Redo | |
| 2402001 Return air grille | 11 | no | $80 | 880 | Redo | |
| 2402001 Return air filter | 6 | no | $100 | 600 | Redo | |
| 2402001 Drawings and airflow report | 1 | sum | 600 | Redo | ||
| 2402001 PE endorsement | 1 | sum | 900 | Redo | ||
| CCTV (72 Pte Ltd) | 1,700 | |||||
| INV 1988 Dahua 4-port PoE NVR with 4TB HDD | 1 | no | $480 | 480 | Move | |
| INV 1988 4MP IR dome camera | 4 | no | $180 | 720 | Move | |
| INV 1988 Cat6 cabling and installation | 1 | sum | 500 | Redo | ||
| Door access (Wise Group) | 1,275 | |||||
| V38770 Hikvision face/card/fingerprint reader | 1 | no | $580 | 580 | Move | |
| V38770 EM locks for frameless glass door, release button, break-glass, PSU and battery | 1 | set | 300 | Maybe | ||
| V38770 Installation (double door) | 1 | sum | 280 | Redo | ||
| V38770 Wired door bell incl. cabling | 1 | no | 55 | Redo | ||
| V38770 Remote release | 2 | no | $30 | 60 | Move | |
| Total, 2024 fit-out (ex GST) | 164,003 | $71.43/sq ft | ||||
We matched each line we could against your own target rates in the Unit Cost Reference. The market band is shown alongside for context. Lines with no matching rate are left out: vinyl flooring, sprinklers, aircon ducting, preliminaries and QP fees. Two things to bear in mind:
| Item | Our 2024 rate | Derrick's target | Market band | Against target |
|---|---|---|---|---|
| Electrical | ||||
| Lighting point | $55 /pt | $55 | $70-180 | Same |
| Emergency-light point | $55 /pt | $55 (lighting point) | $70-180 | Same |
| Twin 13A socket | $90 | $65 | $100-150 | 38% above (+$400) |
| Data point | $120 | $75 | $80-160 | 60% above (+$135) |
| 20A isolator for aircon | $180 | $150 | $100-500 | 20% above (+$120) |
| Light fitting supply + install | $42-65 | $65 | $55-105 | At or below |
| Distribution board | $850 (163A) | $1,500 (100A with DPM and ELR) | $2,500-4,500 | Below: check scope |
| Sub-main cable | about $50/m | about $107/m (accepted as quoted) | $100-115/m | Below |
| LEW drawing / testing | $200 (testing TBC) | $1,150 (accepted as quoted) | $400-1,000 | Below, testing not included |
| Walls and ceiling | ||||
| Gypsum partition with rockwool | $55/m2 (3.0m, no steel) | $50/m2 (4.5m, steel absorbed) | about $100-107/m2 | 10% above (+$1,005) |
| Plywood backing | $108/m2 | $100/m2 | $100-300/m2 | 8% above (+$90) |
| Plaster ceiling | $40/m2 | no target set | $65-97/m2; $40-48 direct | - |
| Emulsion paint | $7.25-8.93/m2 | $6.75/m2 | $21.50-43/m2 | 7-32% above (+$800) |
| Doors and glass | ||||
| 12mm frameless glass swing door | $1,000 | $850 (glass door) | about $1,180-2,100 | 18% above (+$150) |
| Fixed glass panel, aluminium frame | $26/ft2 | $11-14/ft2 (frameless, no frame) | $15-25 frameless; $35-55 framed | About double (+$630) |
| Glass backsplash with ply backing | about $50/ft2 | $11-14/ft2 (tempered glass) | $15-25/ft2 | About 4x (+$670) |
| Swing timber door, single leaf | $900 each | $1,200 is for a double-leaf door | $400-1,200 residential | Not comparable |
| Carpentry | ||||
| Laminate wall panel for signage | $25/ft2 | $12-16/ft2 | $15-40/ft2 | About 75% above (+$520) |
| Timber trellis feature wall, curved, light cove | $23/ft2 | $12-16/ft2 | $15-40/ft2 | About 65% above (+$2,880) |
| Pantry wall-hung cabinet | about $204/ft | $120/ft (half-height) | $130-220/ft | 70% above (+$1,100) |
| Full-height storage cabinet | about $373/ft | $150/ft (full height) | $210-400/ft | About 2.5x (+$660) |
| Pantry base cabinet with solid-surface top | about $369/ft | $120/ft (half-height) | $130-220/ft | About 3x (+$3,310) |
| Reception shoe cabinet, open, 1.5m high | about $362/ft | $150/ft (shoe cabinet) | $130-380/ft | About 2.4x (+$2,300) |
| Two-tier serving counter | about $583/ft | $120/ft (console / half-height) | $110-280/ft | About 5x (+$2,120) |
| Feature open bookshelf, 2.1 x 2.1m | about $610/ft | $150/ft (full height) | $210-400/ft | About 4x (+$3,170) |
| Wash-basin counter with solid surface and mirror | about $1,180/ft | $120/ft (half-height) + mirror | $130-220/ft + mirror | About 9x (+$4,180) |
| Fees | ||||
| Renovation management and design fee | $8,000 | $3,000-5,000 (supervision) | - | +$3,000-5,000 |
Prepared by JY with our CFO model. The workings and data are available on request.